










|
PRESS RELEASES
Water and Waste Water October Supplement
South Leinster DBO Contract
Introduction
Carlow County Council, in partnership with Kildare County Council,
Kilkenny County Council, Laois County Council, South Tipperary County
Council, Wexford County Council, Wicklow County Council and Ballacolla,
Ballypickas, Ballinabranna, Ballyellen, Glynn St. Mullins, Ballycallan,
Castlewarren, Clifton, Cuffesgrange, Windgap, Toor, Baltboys, Hempstown,
Humphreystown, Lambe Tinode, Manor Kilbride, Oldcourt, Tombrean-Umrygar,
Ballinagate, Gormanstown-Usk, Lipstown-Narraghmore, Leinster Lodge,
Blackstairs, Templeudigan, The Rock and Barrowmount Group Water
Supply Schemes, decided to undertake a project, the objective of
which was to improve the provision of piped water supplies to rural
areas in the seven counties. The number of private Group Water Supply
Schemes and Public schemes participating in the project (approximately
35) is unique. The Project will be implemented under a design/build/operate
contract with EPS Pumping & Treatment Systems being the Private
Partner, Main and Operating contractor for the 22 years project
duration.
Tom Ruddy, EPS’s Director explains that the task of designing,
building and operating on such a diversified scale has led to many
challenges for his company. Water is an essential commodity, existing
sources and supplies must be maintained whilst replacement, refurbishment,
or new build treatment and pumping systems are put in place.
In evaluating the project’s planning requirements EPS have
divided the 35 schemes into different categories using various Civil
Subcontractors to carry out packages of work such as “Pipelines”,
“Reservoirs”, “Precast sump & Tanks”,
“Buildings”, and Ancillary Concrete Works and Finishes.
This provides EPS with a flexible resource pool that can be deployed
on one or a number of sites as the project planner requires.
Planning submissions have had to be prepared for eight different
planning authorities for projects in the respective counties. This
entails dealing with environmentally sensitive sites in regions
such as the Blackstairs Mountains or the Slaney Valley. Plant structures
have to “blend in” with the local environment and be
unobtrusive yet functional. This poses challenges for the designers
and the planners to get the balance right between wants and needs.
The process design phase has had to be completed before the planning
submission stage, therefore, the lead in times for all these requirements
is crucial so that the “window for planning approval”
is not interfered with. Interface with the Clients Representative
to ensure compliance with the Employers requirements is adhered
to and yet allowing flexibility for design change resulting from
changing raw water and process requirements is vital.
When you are dealing with potentially 35 different design submissions
a format has to be devised to streamline the process to allow sufficient
time for review and approval. Obviously making 35 submissions en
masse is not practical and here again an agreed “batch programme”
is developed to ensure sufficient resources are available at both
Clients Representative and Contractor level.
EPS is unique amongst the panel of Irish DBO contractors who could
undertake such a diverse range of schemes as it carries “In
House” its own Process, Engineering, Mechanical and Electrical,
design engineers who work hand in hand with their “In House”
Plant Manufacturing” facility. This means that very little
of the work (other than civil works) has to be sub-contracted out
to outside contractors. The on-site installation and commissioning
crews are resourced from EPS’s facilities at Mallow Co Cork,
Mountrath Co Laois, Naas Co Kildare, Ballyhaunis Co Mayo and Cookstown,
Co Tyrone (M.C.C. manufacturing facility).
EPS owns the Licence Rights to “Culligan Process Treatment
Equipment” through their acquisition of “Culligan’s
Irish arm” AH Cullen Water Treatment.
 |
The selection of diverse range of Water Treatment
processes for 35 separate schemes has to be tailored with the
needs of the operation and maintenance of the schemes by EPS
for the next 20 years. Process solutions were selected in “batches”
to suit Raw Water quality, Type of source and End user requirements,
from Boreholes to Rivers, Springs and Lakes, each having very
different characteristics, chemistry and treatment requirements. |
Requirement definitions included, power supply availability, (existing
or new single or three phase) and process suitability for power
available.
 |
Processes chosen include, DAF/Filtration proceeded
by chemical flocculation, Pressure Filtration with options
for Iron and Manganese removal, Colour and Turbidity.
Disinfection using liquid chloros and pre/post Aeration
Precipitation aids where required are integrated into the
Process Design for the specific application.
|
Where processes produce residual sludge or waste wash water, recycling
or reduction of spent product is incorporated into the designs with
membrane barriers on the wash water recycle returns for crypto inhibition.
Surplus sludge is stored on site for removal by operations mobile
tanker for dewatering and disposal off site at an EPS facility.
The EPS Operations and Maintenance team comprising Process Scientists,
Environmental engineers, Instrumentation technicians and Operators
have a major input into the design process and will also be engaged
to assist in the process commissioning and handover of the schemes
prior to the operation and maintenance of the schemes taking place.
Each site has a PLC interface with a centralised SCADA system which
communicates via G.S.M. satellite, radio or hardwire link to the
control centre. The system is monitored 24 hrs/day 7 days/week via
the Operation’s Managers “PC anywhere” monitoring
and data display system. “SATNAV” directs the nearest
available technician to the plant in need of attention in response
to fault alerts.
(Footnote: Photos stocking and service resourcing for Divelle
range of schemes and geographical locations)
Tom advises that dealing with such a diverse Client base requires
a different communication skill set than dealing with conventional
“Client Engineering Consultants”. You have to go out
into the community, meet at Community Halls, Parish Meetings, Steering
Group Meetings, Residents Associations, Group Scheme Committees
and County Council Meetings, communicating and advising of activities
in their respective areas before they commence.
People have to know when you intend going onto their land or digging
up a small rural single carriageway road where only the local school
bus may have to pass, or where a funeral cortege has to be respected
and accommodated. There are real rural issues and are important
if communications and goodwill is to be maintained. You have to
be on the ground. Sitting in a project office in Dublin or Cork
or the UK is just not on!!

FootNote: EPS Regional Recources covering needs of 35 bundled
schemes.
Another critical issues for rural dwellers unlike their counterparts
in the cities is the “cost of water”. These rural communities
have to “pay for water” through their group water schemes,
therefore the capital cost and the cost of the Operate and Maintain
of the scheme is of paramount importance whilst a portion is grant
aided by the Department of Environment Heritage and Local Government
the group schemes have to fund their portion of the build and operate
costs also.
The scheme capital cost of €8.5m equates to a capital cost
of approximately €2,000.00 per household (4200 connections
approximately) which provides the end user with a “value for
money” solution at the design build phase and an ongoing operation
and maintain cost per household per m³ cost per household per
m³ used at a very competitive rate.
To summarise the main approach to bidding, gearing up for, designing,
building and operating such a diverse range of schemes and processes
entailed EPS having :
- Strong financial & economic standing. This is necessary
to resource and build such a large range of sites, projects, to
the taking over stage and the ongoing 20 year operation and maintenance
of the schemes.
- Extensive technical experience & personnel familiar with
the requirements of water treatment technologies for such a diversified
range of water schemes.
- Competitiveness in the delivery of projects to make such a
diverse range of projects economical from both the capital and
ongoing operation cost point of view.
- Network of support services, branches, suppliers and trade
partners to handle the complex requirements of existing and new
scheme interfaces.
- Multi team approach to civil sub contractors for flexibility
and resource requirements to meet the multi site – construction
and completion requirements.
- Over 30 years experience working for group water schemes throughout
Ireland providing an understanding of local issues, requirements
working in partnership with the communities.
The South Leinster Bundle is part of the Governments “Rural
Water Delivery Programme” which EPS have been to the forefront
on delivering schemes in West Cavan (8 Bundles), South West Cavan
(4 Bundles), Lough Annagh GWS, Clare Schemes (4 Bundles), Limerick
Schemes (33 Bundles).
As each bundle is so diversified it is important to have built
up a reservoir of information on process Proven Technologies to
meet the differing ratio water requirements and to apply them successfully
to delivering clear safe water to the EU Directive water requirements
for the future. EPS are confident they can deliver on this ambitious
Government programme. |